A: ProjectLibre automatically creates the Gantt Chart. The tasks just need to be created. To create a task follow steps below.
- Go to Task > Gantt
- In the next available vacant row type the name of task in the Name column.
- Input the hours days in Duration. Type h after the number for hours and d for days. If no letter is provided, it defaults to days. If hours is inputted it is converted into days using 8 hours to a day.
- Input the start date in Start.
- Finish date will automatically be determined by adding duration to the start date. ProjectLibre will automatically skip weekends. If you manually adjust Finish date, Duration will be recomputed.
- To set a task to be sub-task, right the task and click Indent. Indented tasks becomes child tasks. Child tasks can have their own child tasks and so forth. Use Outdent to change a child task to a parent task.
- In Predecessors, indicate the row numbers of the tasks that need to be completed before this task can be started
- In Resource Names, indicate the project members who will work on the task